Pre-mortem: How the UK Department of Health's Digital Team Imagined Project Failure Before Launch

The UK Department of Health and Social Care's digital team ran a 2-hour pre-mortem before its private beta, turning risks and opportunities into concrete tasks in the backlog.

By Oemah Solution Editorial 5 min read

This article was prepared with AI assistance from the official sources listed below, and checked automatically before publication.

Many new software projects only discuss risk after problems appear. There is a cheaper way: imagine failure first. The Digital health and social care blog of the UK's Department of Health and Social Care (DHSC), in a post dated 20 September 2018 by Colin Pattinson, describes how the team ran a pre-mortem workshop just before the private beta of their service. The post says the method was inspired by the Atlassian playbook, with a few adaptations.

What is a pre-mortem

A post-mortem is held after something has ended. A pre-mortem is held on a project that has not yet run. The team imagines the project has become a total disaster or a resounding success, then works backwards to trace how that outcome came about.

According to the author, reasons for doing it include:

  • nobody wants to be responsible for failure, so preventing it is worth a few hours of time;
  • the team may be missing opportunities that are actually there;
  • people who are too close to the project need a fresh perspective;
  • problems are confronted before they damage the project later on;
  • the result is practical actions that can be assigned straight away.

Participants are not limited to the core team. The author recommends inviting stakeholders and people on the edges of the service, because the more varied the viewpoints, the greater the chance of finding what has been overlooked. Real users can also be invited, although the team itself has not yet done so.

How to run it

Preparation starts several weeks beforehand: invitations are sent, a sufficiently large room is booked, and the session is scheduled for 2 hours. The day before, participants receive warm-up questions, for example:

  • what could make us late to launch?
  • what has already made us nervous?
  • who could own each of the biggest risk areas?
  • what would a huge success look like if the project exceeded its targets?

Agenda on the day:

  • a 5-minute introduction and 5 minutes of context-setting, namely moving forward to winter 2020, when the new service has been running for 6 months;
  • the team is split in two for 30 minutes: the failure team writes down ignored warning signs and mistaken assumptions, while the success team writes down positive impacts and unexpected successes, all on post-it notes;
  • 20 minutes of cross-challenge: each team presents its version, then the other team pushes it to be more extreme;
  • a 10-minute dot-vote;
  • 30 minutes for practical actions, 10 minutes for sharing, a 5-minute wrap-up and a 5-minute retrospective.

In the vote, each participant gets 5 votes and must choose at least one risk and one opportunity. The result is the top 3 risks and top 3 opportunities. Participants are directed to choose things the team can influence. For example, the risk of one of the offices suddenly disappearing was set aside because it is almost entirely outside the team's control.

Pitfalls to avoid

  • Actions that are too general. Statements such as "email the minister" are not permitted. An action must state when it will be done, what will be communicated, and the expected outcome.
  • Stopping at discussion. In this case, assignment was delayed because time ran out, so it was settled at the following week's team planning.
  • One post-it holding many ideas. The author suggests one idea per post-it so that presenting and voting are easier.
  • A divided facilitator. With one facilitator having to support two teams, the help of a second person is useful.

The author also notes that the teams can be swapped after the vote so that participants experience both roles, and that a creative warm-up activity (the team used a paperclips exercise) helps if time allows.

How to apply it in teams and agencies

After the workshop, the author copied the contents of the post-it notes into Trello. They created columns for the top risks and opportunities and a column for all actions, with action cards linked to the relevant risk or opportunity card. At sprint planning, each action was reviewed and some were added to the current sprint. The team also committed to reviewing the results again 6 months later.

For development teams and clients in Indonesia, this pattern can be applied before the go-live of a public service or internal system:

  • schedule a 2-hour session with simple equipment: just post-it notes and a comfortable room;
  • involve non-technical stakeholders so that blind spots are easier to see;
  • determine an owner for each risk area, and make sure tasks enter the backlog with a clear deadline;
  • schedule a follow-up review to assess what has been done.

The author concludes that even in the worst-case scenario, the team has only taken 2 hours out of its routine to look at risk from a new perspective. The expected result is a team that is more energised to patch gaps in the plan and capture opportunities that were missed.

#pre-mortem#risk management#agile#sprint planning#work culture